Turkish power plant must pay $120m: SC

Published
0

ISLAMABAD, Nov 26: The Supreme Court settled a repayment dispute on Monday, directing the National Accountability Bureau to recover $120 million from a 232MW barge-mounted Turkish rental power plant.

NAB Director General (Operations) Shahbaz Bhatti informed a three-judge bench that $120m was outstanding against the plant, Karkey Karadeniz Elektrik Uretin AS Turkey. But NAB Prosecutor General K.K. Agha said that the final decision had to be taken by the bureau’s chairman.

The bench comprising Chief Justice Iftikhar Muhammad Chaudhry, Justice Gulzar Ahmed and Justice Sheikh Azmat Saeed had taken up the matter after Makhdoom Faisal Saleh Hayat claimed in a letter that the Turkish project needed to settle $243m but NAB had allowed the ship to leave Pakistan without paying the amount.

On Nov 20, the court had asked Mr Hayat and NAB officials to sit together and reconcile the payable amount that was estimated to be $120m after calculations. Mr Hayat objected, saying according to his estimate the amount was $128m but the court said it would not go into the nitty-gritty of the matter.

Anchored at Port Qasim in Karachi, the power plant was part of an initiative the government had approved to generate approximately 1,206MW through rental power projects as a stopgap arrangement.

But on March 30, the Supreme Court held the power policy and RPP contracts as non-transparent and ordered the NAB chairman to proceed with corruption references against those who were at the helm of affairs when the contracts were signed between 2006 and 2008.

The court said the NAB chairman would be responsible in case the estimation increased later.

The chief justice said Mr Hayat had unearthed a big scam in the power sector which would serve as deterrence for other departments.

Justice Gulzar said that under the agreement the power plant was the property of Karkey in Pakistan. He inquired from the NAB prosecutor general how the money would be recovered if the ship left. The prosecutor said the bureau would take bank guarantee from Karkey. When the court observed that NAB had given an undertaking that unless the entire outstanding amount was paid the ship would not be allowed to sail from Pakistan, the PG reminded it that the bureau had withdrawn the undertaking.

Opinion

Editorial

Terrorist havens
07 Aug, 2026

Terrorist havens

DESPITE the use of both carrots and sticks by the international community, the Afghan Taliban refuse to cut their...
Mineral wealth
Updated 07 Aug, 2026

Mineral wealth

Any future agreements involving critical minerals must be subjected to rigorous legal, financial and technical scrutiny.
Growth denied
07 Aug, 2026

Growth denied

THE Sindh government’s agreement with the World Bank to combine health, nutrition, sanitation, social protection...
Need for dialogue
06 Aug, 2026

Need for dialogue

THE interior minister’s comments at an Islamabad seminar last week have sparked many a conversation about the ...
Bad press
06 Aug, 2026

Bad press

THE government’s move to impose restrictions on international media will not only alienate the foreign press, it...
Automobile concerns
06 Aug, 2026

Automobile concerns

PAKISTAN’S automobile industry is at a critical juncture. Sharp cuts in tariffs on the import of completely built...