LAHORE: Prime Minister Nawaz Sharif has given approval for two additional coal-fired power plants in Gadani under independent power producer (IPP) mode.

The prime minister was presiding over a meeting to review the pace of work on Gadani power project here on Saturday.

He said sufficient funds would be allocated for the projects. He also appreciated Chinese investment in energy sector and especially Gadani Power Park.

Sharif said attractive tariff had drawn foreign investors in coal-fired power projects.

Earlier, the premier was given a briefing on the status of the project. He was informed that the feasibility study of the infrastructure installation would be completed by the end of next month which included geo-technical investigation, water resource survey, jetty break water and cooling water intake system.

The environment impact system study will be completed by June 30.

The work on land levelling and grading on the site would start within three weeks and completed in as many months. The prime minister was also briefed about the coal handling and conveying system infrastructure would be installed in 22 months. Similarly, jetty breakwater and allied infrastructure would be completed in 32 months.

Published in Dawn, May 25th, 2014

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Geopolitical games
Updated 18 Dec, 2024

Geopolitical games

While Assad may be gone — and not many are mourning the end of his brutal rule — Syria’s future does not look promising.
Polio’s toll
18 Dec, 2024

Polio’s toll

MONDAY’s attacks on polio workers in Karak and Bannu that martyred Constable Irfanullah and wounded two ...
Development expenditure
18 Dec, 2024

Development expenditure

PAKISTAN’S infrastructure development woes are wide and deep. The country must annually spend at least 10pc of its...
Risky slope
Updated 17 Dec, 2024

Risky slope

Inflation likely to see an upward trajectory once high base effect tapers off.
Digital ID bill
Updated 17 Dec, 2024

Digital ID bill

Without privacy safeguards, a centralised digital ID system could be misused for surveillance.
Dangerous revisionism
Updated 17 Dec, 2024

Dangerous revisionism

When hatemongers call for digging up every mosque to see what lies beneath, there is a darker agenda driving matters.