Islamabad Metro bus project cost may escalate to Rs50bn

Published September 27, 2014
.— AFP file photo
.— AFP file photo

RAWALPINDI: The Rawalpindi Development Authority (RDA) has started revising the budget of the metro bus project as the estimated cost is likely to go up from Rs44.21 billion to Rs50 billion.

A senior official of the RDA told Dawn that increase in land and construction material cost, purchase of escalators for bus stations, relocation of shrine on Sixth Road and bus depot land were some of the factors that had contributed to increasing the project cost.

Know more: Metro Bus or Mars: The problem with our priorities

No work has taken place on Parade Lane and Blue Area for the last two months due to the sit-ins by Pakistan Tehreek-i-Insaf (PTI) and Pakistan Awami Tehreek (PAT), the official said, adding that the contractor was demanding payment for the extra days needed to complete the project.

He said that the relocation of gas and water pipelines and discovery of lines that had previously not been accounted for at Peshawar Mor and Constitution Avenue had also increased the cost under this head from Rs2.1 billion to Rs4 billion.

The sit-ins have also resulted in road blockade, forcing contractors to buy iron and cement from local industries at prices higher than those quoted in the agreement. Some portions of the ongoing project have been damaged at Parade Lane for which contractors have demanded compensation.


Political unrest in the capital blamed for increase in expenses


For land acquisition, he said Rs1.2 billion had been allocated, but now the cost has increased to Rs2 billion.

He said earlier, a shrine on Murree Road was not falling on the route of the bus service but later that area was also included due to which the government had to acquire more land and compensate the custodian of the shrine.

A total of 27 kanals, including 19 kanals of private land, will be acquired for the construction of bus stations on Murree Road. The 23.2km-long elevated road will have 10 bus stations in Rawalpindi and 14 in Islamabad.

When contacted, Commissioner Rawalpindi and Project Director Metro Bus Project Zahid Saeed said the RDA was working as per its plan. He admitted that work was slow because of political unrest in Islamabad.

He said work on I.J. Principal Road and 9th Avenue was also progressing at a slow pace due to relocation of graveyard and acquisition of land for metro bus depot. However, he said work would pick up pace after the Islamabad High Court allowed relocation of the graveyard.

He said the RDA managed to convince the custodian of the shrine on Sixth Road to relocate the grave and in this regard, payments had been made to him.

However, he said the RDA had called a meeting of contractors on Sunday to review work on all eight packages of the metro bus project. He said all hurdles to the project would be removed soon.

Published in Dawn, September 27th , 2014

Opinion

First line of defence

First line of defence

Pakistan’s foreign service has long needed reform to be able to adapt to global changes and leverage opportunities in a more multipolar world.

Editorial

Eid amidst crises
Updated 31 Mar, 2025

Eid amidst crises

Until the Muslim world takes practical steps to end these atrocities, these besieged populations will see no joy.
Women’s rights
Updated 01 Apr, 2025

Women’s rights

Such judgements, and others directly impacting women’s rights should be given more airtime in media.
Not helping
Updated 02 Apr, 2025

Not helping

If it's committed to peace in Balochistan, the state must draw a line between militancy and legitimate protest.
Hard habits
Updated 30 Mar, 2025

Hard habits

Their job is to ensure that social pressures do not build to the point where problems like militancy and terrorism become a national headache.
Dreams of gold
30 Mar, 2025

Dreams of gold

PROSPECTS of the Reko Diq project taking off soon seem to have brightened lately following the completion of the...
No invitation
30 Mar, 2025

No invitation

FOR all of Pakistan’s hockey struggles, including their failure to qualify for the Olympics and World Cup as well...