ISLAMABAD: As the government may be expecting early commissioning of first LNG terminal, the Engro Terminal Pakistan Limited – the contractor and operator – has complained of non-fulfilment of at least 10 contractual obligations by the government and the Sui Southern Gas Company Limited (SSGC).

In a complaint to Federal Minister for Petroleum Shahid Khaqan Abbasi, Petroleum Secretary Abid Saeed, SSGC Chairman Ismail Miftah, and SSGC MD Shoaib Warsi, the chief executive officer of Engro Elengy Terminal Limited (EETL), Shaikh Imranul Haque, has conveyed concerns that delay in resolution of commitments was “now resulting in delay of first gas date and our inability to progress the project as per schedule.”

According to the petroleum minister, the EETL was required to achieve commercial operation of the terminal by the end of March 2015 under the agreement. However, he said, the government was pushing it to complete the terminal by the end of December or January.

Mr Shaikh said that the government had directed the SSGC to hire requisite legal support required to close out the direct agreements and options agreement, draft of which has been pending with the SSGC.

Moreover, agreements were required to be finalised with all the parties before Aug 28, 2014. These included Marine Construction Direct Agreement, Pipeline Construction Direct Agreement, Port Qasim Lease Direct Agreement, Bridge Floating Storage and Regasification Unit (FSRU) Charter Direct Agreement, Long term FSRU Charter Direct Agreement, Port Qasim Authority Implementation Direct Agreement and EVTL Support Services Direct Agreement.

Likewise, option agreements were also needed to be finalised. These included agreement between FSRU ownder, SSGC and EETL regarding the grant of a purchase option in favour of SSGC by the FSRU owner with respect to long term FSRU and agreement between SSGC and EETL regarding grant of a purchase option in favour of SSGC with respect to Connecting Pipeline, the unloading facilities and other relevant facilities by EETL.

The EETL chief said the condition of use was also not finalised before signing of an agreement on April 30 and it was mutually agreed between SSGC and EETL that this schedule will be finalised within 30 days i.e. by May 29. However, due to expiry of consultancy with QED consultants, this schedule was still pending.

The EETL has also complained that it was to be provided with standby letter of credit (SBLC) by Aug 28 but there was no progress on the matter.

On top of that, the company has complained that it has not yet been taken into confidence over development of billing and commissioning procedures and the procedure for LNG handling for multiple customers of EETL and no response had come from SSGCL despite repeated reminders.

Oil and Gas Regulatory Authority (Ogra) had formally issued a licence to EETL for construction of a terminal at Port Qasim for landing and re-gasification of LNG to be imported next year.

This was one of the most critical stages towards import of about 500mmcfd (million cubic feet per day) LNG originally targeted for November 2014 by the PML-N government. The target was revised to April 2015.

Published in Dawn, September 30th , 2014

Opinion

Editorial

Rushed legislation
Updated 06 Nov, 2024

Rushed legislation

For all its stress on "supremacy of parliament", the ruling coalition has wasted no opportunity to reiterate where its allegiances truly lie.
Jail reform policy
06 Nov, 2024

Jail reform policy

THE state is making a fresh attempt to improve conditions in Pakistan’s penitentiaries by developing a national...
BISP overhaul
06 Nov, 2024

BISP overhaul

IT has emerged that the spouses of over 28,500 Sindh government employees have been illicitly benefiting from BISP....
Smog hazard
Updated 05 Nov, 2024

Smog hazard

The catastrophe unfolding in Lahore is a product of authorities’ repeated failure to recognise environmental impact of rapid urbanisation.
Monetary policy
05 Nov, 2024

Monetary policy

IN an aggressive move, the State Bank on Monday reduced its key policy rate by a hefty 250bps to 15pc. This is the...
Cultural power
05 Nov, 2024

Cultural power

AS vital modes of communication, art and culture have the power to overcome social and international barriers....