LAHORE: At least 53 per cent of civil works of the Tarbela Extension has been completed and progress on the power house stands at 55pc.

Project General Manager Iqbal Masood Siddiqui told a briefing during a visit of Wapda chairman Zafar Mahmood.

He said the progress was 70pc on the generating unit No 17, whereas unit No 16 achieved 44pc and unit No 15 got 37pc.

He said that every effort was being made to complete the project as per the accelerated construction programme and it should benefit the country by $300 million by utilizing additional flows of water by 2017. Reviewing the construction work, the chairman said the Tarbela Extension Hydropower Project was of vital importance to help overcome electricity shortages in the country in line with the federal government’s resolve.

The chairman directed the project authorities to closely monitor the progress on the accelerated programme, and make sure that the contractors adhere to the time lines in letter and spirit so as to complete the project by June 2017 ahead of its original schedule.

The Tarbela 4th Extension Hydropower Project was being constructed on tunnel No 4 of the Tarbela Dam.

The project will increase generation capacity of the Tarbela Hydel Power Station from 3,478MW to 4,888MW after installation of three units -- with installed capacity of 470MW each.

The World Bank is providing $840 million for construction of the project. On completion, the Tarbela Extension Hydropower Project will add 3.84 billion units of low-cost electricity to the national grid per annum. Annual benefits of the project have been estimated at about Rs30bn.

Published in Dawn, March 11th, 2016

Opinion

Editorial

Security challenges
08 Sep, 2024

Security challenges

THE sentiment expressed was commendable, but will positive words also shape positive policies? That is the big...
Irsa law changes
08 Sep, 2024

Irsa law changes

THE proposed controversial changes to the Irsa law, which aim to restructure the water regulator, will significantly...
Gaza polio campaign
08 Sep, 2024

Gaza polio campaign

AFTER 11 months of savage Israeli violence, Gaza’s health and sanitation systems have collapsed. As a result, the...
Furtive measures
Updated 07 Sep, 2024

Furtive measures

The entire electoral exercise has become riddled with controversy, yet ECP seems unwilling to address the lingering questions about the polls.
PCB hot seat
Updated 07 Sep, 2024

PCB hot seat

MOHSIN Naqvi is facing criticism from all quarters. Pakistan’s cricket board chief, who is also the country’s...
Rapes most foul
07 Sep, 2024

Rapes most foul

UNTIL the full force of the law is applied on perpetrators, insecurity will stalk Pakistan’s girl children and...