MULTAN: Metro Bus Project Technical Adviser Sabir Khan Sadozai says carpeting of the Metro Bus Track’s carriageway is under way.

Giving a briefing here on Sunday, he said carpeting of Bosan Road from Science College to Chungi No 9 had been completed, while carpeting of the other side of the same road is under way. It will be completed within two days.

He said the road work and patchwork between Chungi No 6 and Sabzazaar Colony had been completed and road was being prepared with asphalt.

He said 90pc carpeting work on both sides of the carriageway from Sabzazaar Colony to Bahauddin Zakariya University had been completed, while carpeting work was in its final stage from Chowk Kumharanwala to Allah Wasaya Chowk.

Published in Dawn, May 23rd, 2016

Editorial

A hasty retreat
28 Nov, 2024

A hasty retreat

POLITICAL immaturity has cost the PTI dearly once again. It appears things may not have come to this had Bushra ...
Lebanon truce
28 Nov, 2024

Lebanon truce

WILL it hold? That is the question many in the Middle East and beyond will be asking after a 60-day ceasefire ...
MDR anomaly removed
28 Nov, 2024

MDR anomaly removed

THE State Bank’s decision to remove its minimum deposit rate requirement for conventional banks on deposits from...
Islamabad march
Updated 27 Nov, 2024

Islamabad march

WITH emotions running high, chaos closes in. As these words were being written, rumours and speculation were all...
Policing the internet
27 Nov, 2024

Policing the internet

IT is chilling to witness how Pakistan — a nation that embraced the freedoms of modern democracy, and the tech ...
Correcting sports priorities
27 Nov, 2024

Correcting sports priorities

IT has been a lingering battle that has cast a shadow over sports in Pakistan: who are the national sports...