SHANGLA: Delay in inauguration of the 17-megawatt Ranolia hydropower project owing to lack of interest by the federal and Khyber Pakhtunkhwa governments has deprived the national grid of getting 17MW of electricity for the last one year.

Sources said that despite completion of work for the last one year the project was still made operational. Work on the Asian Development Bank-funded power project at Ranolia in Kohistan district near Bisham city of Shangla district was started in 2013 and completed in March 2015. The Pakhtunkhwa Energy Development Organisation (Pedo) has constructed the Ranolia Khwar project at a cost of Rs4 billion.

The sources said that local people had stopped work on erecting electricity poles till provision of the compensation amount of up to Rs3 million for their land. The government had fixed Rs300,000 to Rs400,000 for 6ft to 10ft land for each tower. Besides, the local people have threatened to stop installation of poles till solution of their grievances.


Asad Umar claims centre responsible for the delay


Official sources at the Renolia project told Dawn that installation of electricity Tower No 6 in Pallas tehsil and Tower No 2 in Pattan tehsil were yet to be completed due to resistance by the local landowners. They said that handover of the project to the federal government had been delayed for the last one year owing to delay in resumption of work on the two disputed poles.

Pakistan Tehreek-i-Insaf central leader Asad Umar has claimed on social media (his official page) that the federal government was adopting delaying tactics in owning the Ranolia project. However, the people of Kohistan and Shangla have demanded of both the federal and provincial governments to make the project operational as soon as possible.

Assistant director Ranolia hydropower project Said Nabi told this correspondent that work on the project had been completed in 2015, but inauguration was delayed due to hurdles created by people of Kohistan in Pallas and Pattan tehsils. He said that all towers had been installed except two where the landowners were demanding more money than the rate fixed by the government.

He said that the administration had assured them to summon and convince the landowners to allow installation of poles.

When contacted, PTI lawmaker Shaukat Yousafzai said that the issue would be resolved on priority and Ranolia power project would soon start electricity supply to the national grid. He criticised the federal government for delaying tactics to own the Pedo’s project through NTDC. He said that PTI chairman Imran Khan would inaugurate the Ranolia project soon after Eidul Fitr.

Published in Dawn, July 9th, 2016

Opinion

Who bears the cost?

Who bears the cost?

This small window of low inflation should compel a rethink of how the authorities and employers understand the average household’s

Editorial

Internet restrictions
23 Dec, 2024

Internet restrictions

JUST how much longer does the government plan on throttling the internet is a question up in the air right now....
Bangladesh reset
23 Dec, 2024

Bangladesh reset

THE vibes were positive during Prime Minister Shehbaz Sharif’s recent meeting with Bangladesh interim leader Dr...
Leaving home
23 Dec, 2024

Leaving home

FROM asylum seekers to economic migrants, the continuing exodus from Pakistan shows mass disillusionment with the...
Military convictions
Updated 22 Dec, 2024

Military convictions

Pakistan’s democracy, still finding its feet, cannot afford such compromises on core democratic values.
Need for talks
22 Dec, 2024

Need for talks

FOR a long time now, the country has been in the grip of relentless political uncertainty, featuring the...
Vulnerable vaccinators
22 Dec, 2024

Vulnerable vaccinators

THE campaign to eradicate polio from Pakistan cannot succeed unless the safety of vaccinators and security personnel...