Ukraine moves giant new safety dome over Chernobyl

Published November 30, 2016
A picture shows Chernobyl's New Safe Confinement covering the destroyed 4th block of the Chernobyl nuclear power plant after its installation was completed on November 29, 2016. ─ AFP
A picture shows Chernobyl's New Safe Confinement covering the destroyed 4th block of the Chernobyl nuclear power plant after its installation was completed on November 29, 2016. ─ AFP

Ukraine on Tuesday unveiled the world's largest movable metal structure over the Chernobyl nuclear power plant's doomed fourth reactor to ensure the safety of Europeans for future generations.

The gigantic arch soars 108 metres (355 feet) into the sky — making it taller than New York's Statue of Liberty -- while its weight of 36,000 tons is three times heavier than the Eiffel Tower in Paris.

The $2.2 billion structure sponsored by the European Bank for Reconstruction and Development (EBRD) has been edged into place over an existing crumbling dome that the Soviets built in haste when disaster struck three decades ago.

Ukrainian President Petro Poroshenko was visibly proud at his impoverished and war-torn country's ability to deal with one of the worst vestiges of its Soviet past.

“Many people had doubts and refused to believe that this was possible,” Poroshenko told the festive ceremony held in front of the gleaming new dome. “But my friends, I congratulate you — yes, we did it!”

Radioactive fallout from the site of the world's worst civil nuclear accident spread across three-quarters of Europe and prompted a global rethink about the safety of atomic fuel.

Work on the previous dome began after a 10-day fire caused by the explosion was contained but radiation still spewed out of the stricken reactor.

“It was done through the super-human efforts of thousands of ordinary people,” the Chernobyl museum's deputy chief Anna Korolevska told AFP.

“What kind of protective gear could they have possibly had? They worked in regular construction clothes.”

About 30 of the cleanup workers known as liquidators were killed on site or died from overwhelming radiation poisoning in the following weeks.

The Soviets sought to try to cover up the accident that was caused by errors during an experimental safety check and its eventual toll is still hotly disputed.

The United Nations estimated in 2005 that around 4,000 people had either been killed or were left dying from cancer and other related diseases.

But the Greenpeace environmental protection group believes the figure may be closer to 100,000. Authorities maintain a 30-kilometre-wide (19-mile) exclusion zone around the plant in which only a few dozen elderly people live.

One of the main problems of the Soviet-era response was the fact that it only had a 30-year lifespan. Yet its deterioration began much sooner than that.

“Radioactive dust inside the structure is being blown out through the cracks,” Sergiy Paskevych of Ukraine's Institute of Nuclear Power Plant Safety Problems told AFP.

Paskevych added that the existing structure could crumble under extreme weather conditions.

The new arch should be able to withstand tremors of 6.0 magnitude — a strength rarely seen in eastern Europe ─ and tornados that strike the region only once every million years.

Kiev has complained that European assistance was slow to materialise.

The EBRD found 40 state sponsors to fund a competition in 2007 to choose who should build the massive movable dome.

A French consortium of two companies known as Novarka finished the designs in 2010 and began construction two years later.

The shelter was edged towards the fourth reactor in just under three weeks of delicate work this month that was interrupted by bad weather and other potential dangers.

It will later be fitted with radiation control equipment as well as air vents and fire fighting measures. The equipment inside the arch is expected to be operative by the end of 2017.

“Only then will we begin to disassemble the old, unstable structure,” State Nuclear Regulatory Inspectorate of Ukraine's head Sergiy Bozhko told AFP.

But he said no time frame had yet been set for the particularly hazardous work of removing all the remaining nuclear fuel from inside the plant or dismantling the old dome.

Novarka believes that its arch will keep Europe safe from nuclear fallout for the next 100 years.

Opinion

Editorial

Shortcut tactics
Updated 25 Mar, 2025

Shortcut tactics

IMF’s decision to veto move to reduce retail power tariffs seems to be against interests of middle-class consumers.
Unforced error
25 Mar, 2025

Unforced error

THE state is understandably keen on neutralising the threat posed by various militant and terrorist outfits, but it...
Losing again
25 Mar, 2025

Losing again

WHEN Pakistan’s high-risk Twenty20 approach did not work, there was no fallback plan and they collapsed in a heap...
Climate action
Updated 24 Mar, 2025

Climate action

Waiting for outside help to arrive will only aggravate our climate challenges and not mitigate them.
TB burden
24 Mar, 2025

TB burden

AS the world observes World Tuberculosis Day, we confront the sombre fact that despite being both preventable and...
Unsafe passages
24 Mar, 2025

Unsafe passages

WRETCHED social conditions add an extra layer of cruelty to ordinary lives. The UN’s migration agency says that...