ISLAMABAD: The Rs30 billion worth of much-delayed Golen Gol Hydropower Project in Chitral District of Khyber Pakhtunkhwa is getting ready for power generation in about two months, however locals may not be able to consume the electricity owing to distribution constraints.

Informed sources in the Power Division told Dawn on Tuesday that the first 36-megawatt unit of the project was nearing completion and expected to start generation before Dec 31 under a revised deadline set by former prime minister Nawaz Sharif.

During a visit to Chitral early last year, Mr Sharif had announced dedication of first unit (36MW) to the marble city and people of Chitral and adjoining areas who complained excessive loadshedding, low-voltage and fewer electricity connections.

He had directed Wapda to accelerate project construction and ordered the Peshawar Electric Supply Company (Pesco) to augment distribution system to absorb 36MW electricity from the new unit to meet requirements of the area people.

The sources said while Wapda mobilised additional resources to deliver on the government directive, Pesco struggled on its part to lay lines for supplying additional electricity from Golen Gol to Chitral and adjoining areas at around 22-kilometre distance. Even if Wapda is able to operationalise first unit, “the laxity on part of Pesco can cost dearly to the people in Chitral,” an official said.

“The only action taken by Pesco so far is the submission of a PC-I amounting to Rs5bn to the federal government but was not actively pursuing for its approval by the Planning Commission. When contacted, a Wapda spokesperson said the authority was on schedule to deliver the first unit by December, but declined to comment on the readiness of the distribution company to evacuate power.

The 108MW project was originally planned to start in 1996 but actually commenced construction in 2002 with a completion deadline of 2011. Its approved cost was estimated at Rs7bn in 2002 but was revised to Rs29.1bn in September 2016. As of last month, the project is reported to have achieved 81pc physical progress.

A consortium of international lenders was also funding the project.

Published in Dawn, September 27th, 2017

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Kurram atrocity
Updated 22 Nov, 2024

Kurram atrocity

It would be a monumental mistake for the state to continue ignoring the violence in Kurram.
Persistent grip
22 Nov, 2024

Persistent grip

PAKISTAN has now registered 50 polio cases this year. We all saw it coming and yet there was nothing we could do to...
Green transport
22 Nov, 2024

Green transport

THE government has taken a commendable step by announcing a New Energy Vehicle policy aiming to ensure that by 2030,...
Military option
Updated 21 Nov, 2024

Military option

While restoring peace is essential, addressing Balochistan’s socioeconomic deprivation is equally important.
HIV/AIDS disaster
21 Nov, 2024

HIV/AIDS disaster

A TORTUROUS sense of déjà vu is attached to the latest health fiasco at Multan’s Nishtar Hospital. The largest...
Dubious pardon
21 Nov, 2024

Dubious pardon

IT is disturbing how a crime as grave as custodial death has culminated in an out-of-court ‘settlement’. The...