KARACHI: Attock Cement Pakistan Ltd (ACPL) has started operations of its new production line at Hub, Balochistan.

The production capacity of this line is 4,000 tonnes per day (1.2 million tonnes per annum), the company informed in a filing to the Pakistan Stock Exchange on Tuesday.

A company official told Dawn that $130 million was spent on this expansion, which increases the total plant capacity to 10,000 tonnes per day.

The expansion has been completed in a record 22 months with the entire project constructed and commissioned by the help of Pakistani engineers. It is a brand new Chinese-cum-European hybrid plant.

According to an analyst at BIPL Securities, the company also plans to install a 15-megawatt waste heat recovery power plant to help curtail production costs.

He said with the commissioning of new lines of Lucky Cement and ACPL, cement prices may come under pressure in the southern region.

Published in Dawn, January 10th, 2018

Opinion

Editorial

Military convictions
Updated 22 Dec, 2024

Military convictions

Pakistan’s democracy, still finding its feet, cannot afford such compromises on core democratic values.
Need for talks
22 Dec, 2024

Need for talks

FOR a long time now, the country has been in the grip of relentless political uncertainty, featuring the...
Vulnerable vaccinators
22 Dec, 2024

Vulnerable vaccinators

THE campaign to eradicate polio from Pakistan cannot succeed unless the safety of vaccinators and security personnel...
Strange claim
Updated 21 Dec, 2024

Strange claim

In all likelihood, Pakistan and US will continue to be ‘frenemies'.
Media strangulation
Updated 21 Dec, 2024

Media strangulation

Administration must decide whether it wishes to be remembered as an enabler or an executioner of press freedom.
Israeli rampage
21 Dec, 2024

Israeli rampage

ALONG with the genocide in Gaza, Israel has embarked on a regional rampage, attacking Arab and Muslim states with...