ISLAMABAD: Poor standard of construction has been found in a road project of the China-Pakistan Econo­mic Corridor (CPEC) in Balochistan.

The Zhob-Mughalkot Road (N-50) has two packages and Package-I is being built by M/s Zahid Khan & Brothers (ZKB).

Maqbool Associates, which had submitted the lowest bid, won the contract, but the National Highway Authority (NHA) reportedly awarded it to ZKB, though the latter had offered higher rates, without asking it to match the lowest bid.

Former prime minister Nawaz Sharif had inaugurated the project in January 2016.

It has been learnt that an 11km portion of the 41km Zhob-Killi Khudae Nazar road (Package-I) was badly damaged, while ditches and cracks had also appeared on its other portions.

According to an NHA document, the 41km Zhob-Killi Khudae Nazar road was to be reconstructed by Limak-ZKB Joint Venture at a cost Rs4.8 billion under Package-I, and the 40km Killi Khudae Nazar-Mughalkot road by Maqbool-Zarghoon Joint Venture at cost of Rs4bn under Package-II.

At the same time, two separate projects had been awarded for N-70. A firm, Umar Jan, will construct the road from Qilla Saifullah to Loralai at a cost Rs4.50bn under Package-I, while Maqbool-Zarghoon JV will construct the road from Loralai to Waigum Rud at a cost of Rs3.02bn under Package-II.

According to the NHA document, Maqbool-Zarghoon JV had submitted the lowest bids for all four projects, but it was not considered for Package-I of N-50 and Package-I of N-70 and the contracts had been awarded to the second lowest bidders (ZKB and Umar Jan). Even the second lowest bidders had not been asked to match the lowest bids.

Maqbool-Zarghoon JV has expressed concern over non-consideration of its bids and wrote many letters to the NHA, claiming that the contracts had been awarded ‘illegally’ to the second lowest bidders.

When contacted, an NHA spokesman said the project was under construction and had not yet been completed.

He said: “Such problems/damages do often happen during construction and its rectification remains the responsibility of the contractor/consultant. It is always ensured that all such issues are fully addressed before the project is completed and opened to traffic.”

He said the 81km long Zhob-Mughalkot project was divided into two lots and awarded to ZKB and Maqbool-Zarghoon JV, respectively. Maqbool-Zarghoon JV challenged the award of lot-1 in court where they lost the case and the Islamabad High Court upheld the NHA’s decision.

Although the issue caused a delay in execution of the project, the NHA has managed to overcome unnecessary loss of time and the project was set to complete during the current year.

Published in Dawn, May 7th, 2018

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Smog hazard
Updated 05 Nov, 2024

Smog hazard

The catastrophe unfolding in Lahore is a product of authorities’ repeated failure to recognise environmental impact of rapid urbanisation.
Monetary policy
05 Nov, 2024

Monetary policy

IN an aggressive move, the State Bank on Monday reduced its key policy rate by a hefty 250bps to 15pc. This is the...
Cultural power
05 Nov, 2024

Cultural power

AS vital modes of communication, art and culture have the power to overcome social and international barriers....
Disregarding CCI
Updated 04 Nov, 2024

Disregarding CCI

The failure to regularly convene CCI meetings means that the process of democratic decision-making is falling apart.
Defeating TB
04 Nov, 2024

Defeating TB

CONSIDERING the fact that Pakistan has the fifth highest burden of tuberculosis in the world as per the World Health...
Ceasefire charade
Updated 04 Nov, 2024

Ceasefire charade

The US talks of peace, while simultaneously arming and funding their Israeli allies, are doomed to fail, and are little more than a charade.