PESHAWAR: The Peshawar Bus Rapid Transit project is likely to face further delays as the Peshawar Development Authority’s failure to clear the contractor’s payments has piled up bills amounting to over Rs3 billion, sources say.

The much-anticipated project has witnessed a roller-coaster ride over the last few week with three deadline changes, chaos at the fledgling company setup to run the bus service and the most recent being the authorities’ failure to ensure timely transportation of the prototype bus to the provincial capital.

Sources familiar with the matters told Dawn that long delays in the clearing the bills on part of the project execution agency PDA has led to accumulation of over Rs3 billion for all three reaches of the project.

“The accumulated liabilities for each reach of the project are over Rs1 billion,” the source said.

Sources say bus project facing more delay as PDA not clearing contractor bills

The sources said contractors faced great troubles in making payments to vendors and labourers and for fuel charges.

“The bills have got stuck with the PDA for the last 40 days and the contractors are facing problems in paying their staff and clearing other dues,” a source said.

He said the contractors were incurring charges up to Rs100 million on a daily basis and had no means to adjust huge daily expenditure due to long delays on part of the PDA.

“Due to the cash problems, even work has slowed down to around 20 per cent. It could also delay the project for more than five months,” he said.

He said there was 40-60 days time to clear the contractors’ bills, while the contractors had to borrow items from the market on a daily basis and therefore, the failure to make payments was creating problems for them.

The provincial government has set July 20 as the new deadline for the project’s launch after missing earlier ones.

The sources however said the contractors were struggling pay wages to around 4,000 labourers and for iron, cements and equipment.

The source said usually, the official red tape was responsible for the delay.

The project administration manual provides for the direct payment procedures for making payments to contractors, suppliers of goods and supervision consultants.

It says there are four anticipated large civil works contracts which will be administered by the PDA, while the contractors will submit an invoice along with an interim progress certificate showing the completed civil works for the period.

“The construction supervision consultants will review the interim progress certificate against the contract and endorse the invoice to PDA. Upon satisfactory review, PDA’s Project implementation unit (PIU) will prepare a withdrawal application (WA) for direct payment to the contractor, for signature of loan authorized signatories. The ADB will make payment to the contractor based on the submitted WA,” it reads,

The Peshawar BRT has suffered several delays in the last weeks.

Scheduled to open on April 20, the project was delayed until May, which was also missed.

The KP government was adamant of running a prototype bus on a completed portion of BRT corridor. However, the buses didn’t arrive in the city on time, leading to the sacking of TransPehsawar chief executive officer and the subsequent resignations from the company tasked to run the BRT operations.

A prototype bus being bought at the hefty price of $30,000 has got stuck on the Pakistan-China border for several days. It is unlikely to reach here before the end of the PTI government’s tenure ending shortly.

Sources said the bus project’s cost had jumped to Rs62 billion and the PC-I was being prepared to account for cost escalation.

Earlier, this month, three companies, including Daewoo Pakistan and two Turkish companies, have submitted bids for running BRT operations.

Of this, a Turkish joint venture Compak Temizlik Bilgi Islem Otem Saglik Hiz, Inc. Tic.A.S and Gur.sel. Turizm Tasimilick ve servis ticrat, as has submitted lowest bid of Rs139 per kilometer per bus.

Spokesman for BRT project Ikramullah Gandapur denied delay in the bills clearance.

“It would be a delay once the period exceeds 28 days,” he said, adding that in the current case, the bills were being cleared regularly.

Mr Gandapur said in case of the Peshawar BRT, the bill clearance was a three-stage process, wherein consultant verified bills submitted by the contractor after which the PDA asked the ADB to release the money.

He said the clearance of a bill usually took from one week to 10 days and not more than that.

Published in Dawn, May 23rd, 2018

Opinion

Editorial

Tax amendments
Updated 20 Dec, 2024

Tax amendments

Bureaucracy gimmicks have not produced results, will not do so in the future.
Cricket breakthrough
20 Dec, 2024

Cricket breakthrough

IT had been made clear to Pakistan that a Champions Trophy without India was not even a distant possibility, even if...
Troubled waters
20 Dec, 2024

Troubled waters

LURCHING from one crisis to the next, the Pakistani state has been consistent in failing its vulnerable citizens....
Madressah oversight
Updated 19 Dec, 2024

Madressah oversight

Bill should be reconsidered and Directorate General of Religious Education, formed to oversee seminaries, should not be rolled back.
Kurram’s misery
Updated 19 Dec, 2024

Kurram’s misery

The state must recognise that allowing such hardship to continue undermines its basic duty to protect citizens’ well-being.
Hiking gas rates
19 Dec, 2024

Hiking gas rates

IMPLEMENTATION of a new Ogra recommendation to increase the gas prices by an average 8.7pc or Rs142.45 per mmBtu in...