QUETTA: The National Accountability Bureau (NAB) Balochistan has taken notice of delay and substandard work in the construction of Quetta Water Supply and Environmental Improvement Project (QWSEIP), carried out by the National Construction Limited.

The NCL, despite receiving major amount of the project, did not complete the scheme.

“The revised cost of the QWSEIP was Rs10 billion and the Balochistan government released about Rs9 billion to the NCL, but the company did not complete the project despite receiving the major amount,” Public Health Engineering Department Secretary Zahid Saleem told the Director General of NAB,

Balochistan, Mirza Mohammad Irfan Baig, during a briefing held on Saturday to review the pace of work on QWSEIP and Mangi dam projects.

The DG was informed that the NCL laid down pipelines (1,505km) for distribution of water, but there was no map or drawing and other relevant record available of the projects.

While expressing dissatisfaction over inordinate delay and standard of work in the water project, the NAB director general said that those responsible would be dealt with sternly.

He issued directives to call NCL authorities along with relevant record to ascertain who had caused the loss to the national exchequer by delaying this vital project.

Published in Dawn, September 10th, 2018

Opinion

Editorial

Islamabad march
Updated 27 Nov, 2024

Islamabad march

WITH emotions running high, chaos closes in. As these words were being written, rumours and speculation were all...
Policing the internet
27 Nov, 2024

Policing the internet

IT is chilling to witness how Pakistan — a nation that embraced the freedoms of modern democracy, and the tech ...
Correcting sports priorities
27 Nov, 2024

Correcting sports priorities

IT has been a lingering battle that has cast a shadow over sports in Pakistan: who are the national sports...
Kurram ceasefire
Updated 26 Nov, 2024

Kurram ceasefire

DESPITE efforts by the KP government to bring about a ceasefire in Kurram tribal district, the bloodletting has...
Hollow victory
26 Nov, 2024

Hollow victory

THE conclusion of COP29 in Baku has left developing nations — struggling with the mounting costs of climate...
Infrastructure schemes
26 Nov, 2024

Infrastructure schemes

THE government’s decision to finance priority PSDP schemes on a three-year rolling basis is a significant step...