Work on 32km Darra-Peshawar gas pipeline nears completion

Published January 22, 2019
SNGPL General Manager Arbab Mohammad Saqib being briefed about the gas pipeline project in Peshawar on Sunday. — Dawn
SNGPL General Manager Arbab Mohammad Saqib being briefed about the gas pipeline project in Peshawar on Sunday. — Dawn

PESHAWAR: Work on 32km gas supply line from Darra Adamkhel to Peshawar is nearing completion to augment and address low gas pressure issue of tail-end consumers in nearly half the provincial metropolis, it was learnt here on Monday.

Engineers working at the sales meter station Peshawar, while briefing SNGPL General Manager Arbab Mohammad Saqib disclosed that work on the 16-inch diameter pipeline directly linking gas field in the southern districts of KP with Peshawar would be ready by early next week, much ahead of its scheduled date of completion.

The project, costing Rs560 million, was originally scheduled to be completed by June 2019.

The pipeline traverses some of the most difficult and risky terrains including areas once seen as badly affected by militancy to reach all the way from the arms manufacturing market to Peshawar.

The new pipeline would augment gas pressure in areas like University Town, Hayatabad, Regi Model Town and could be further extended beyond to provide gas to consumers as far as in the tribal districts of Khyber, Mr Saqib was told.

Similarly, a 16-inch diameter pipeline spanning over 8.1 kms costing Rs160 million would provide direct gas to the industrial estate near Hayatabad and enhance the already existing gas system.

Mr Saqib said that plans were afoot to separate CNG stations from domestic consumers’ supply line.

Besides, the upgradation of 27km pipeline along the under-construction BRT route had already been commissioned.

The SNGPL GM, while speaking on the occasion said that old pipeline system laid down in the 1970s and 1980s had already been upgraded at a cost of Rs253 million.

He added that 90 per cent of work on the pipeline had already been completed costing Rs300 million through which major lacunas in the gas supply system would be addressed.

“Our workers and engineers are working day and night to complete the projects on war footing, he said.

Published in Dawn, January 22nd, 2019

Opinion

Editorial

Tribunals’ failure
Updated 19 Nov, 2024

Tribunals’ failure

With election tribunals having failed to fulfil their purpose, it isn't surprising that Pakistan has not been able to stabilise.
Balochistan MPC
19 Nov, 2024

Balochistan MPC

WHILE immediate threats to law and order must be confronted by security forces, the long-term solution to...
Firm tax measures
19 Nov, 2024

Firm tax measures

FINANCE Minister Muhammad Aurangzeb is ready to employ force to make everyone and every sector in Pakistan pay their...
When medicine fails
Updated 18 Nov, 2024

When medicine fails

Between now and 2050, medical experts expect antibiotic resistance to kill 40m people worldwide.
Nawaz on India
Updated 18 Nov, 2024

Nawaz on India

Nawaz Sharif’s hopes of better ties with India can only be realised when New Delhi responds to Pakistan positively.
State of abuse
18 Nov, 2024

State of abuse

The state must accept that crimes against children have become endemic in the country.