Descon, CGGC awarded Mohmand Dam Project

Published March 27, 2019
The project will add 800MW to the national grid. ─ APP/File
The project will add 800MW to the national grid. ─ APP/File

LAHORE: The Water and Power Deve­lopment Authority (Wapda) has finally awarded the contract for civil and electro-mechanical construction works at the Mohmand Dam Project to a joint venture between China Gezhouba Group of Companies (CGGC) and Descon Pakistan.

“Wapda has successfully realigned the project after a delay of decades, removing the legal, financial and technical snags. However, the project will phenomenally contribute towards water, food and energy security of Pakistan,” said the Wapda chairman while speaking on the ceremony held to announce the project.

“By awarding the contract worth Rs183.523 billion, we have saved Rs18bn from the approved PC-I”, claimed the Wapda in a press release.

Explore: What is the conflict of interest in the award of the Mohmand Dam contract?

The contract was approved on Feb 22, however, the agreement was formally signed between the representatives of Wapda, CGGC and Descon Pakistan on Tuesday.

It will add 800MW to the national grid

“We are committed to completing the project as early as possible to cope with the ever increasing needs of water and electricity in the country,” said Wapda Chairman Retd. Lt. Gen Muzammil Hussain. He added that construction of Mohmand Dam will go a long way in stabilising the national economy besides alleviating poverty and ushering in an era of development for the area surrounding the project.

Explore: Bidding process for Mohmand dam project sparks controversy

The project was marred by controversy after opposition parties cited conflict of interest as Wapda awarded the project to Descon, which is owned by Adviser to Prime Minister Abdul Razak Dawood.

Opposition leader and Chairman PML-N Shahbaz Sharif termed the government’s act of cancelling the project’s second bidding on technical grounds “a bid to facilitate adviser’s company [Descon]”. He also demanded the government to review the bidding process but the decision, which was based on a single bid, was defended by government saying the process was lawful.

The project is historic and unique in nature as it is being constructed on Swat River in Mohmand district of Khyber Pakhtunkhwa and is scheduled to be completed in five years and eight months.

On completion, the dam will store about 1.2 million acres feet (MAF) of water, generate 800MW of hydel electricity and help contain floodwaters in Peshawar, Charsadda and Nowshera.

Besides supplementing 160,000 acres of existing land, about 16,700 acres of new land will also be irrigated because of the dam. In addition, the project will also provide 300m gallons of drinking water to the residents of Peshawar. Annual benefits of the project have been estimated at Rs51.6bn.

Published in Dawn, March 27th, 2019

Opinion

Editorial

Geopolitical games
Updated 18 Dec, 2024

Geopolitical games

While Assad may be gone — and not many are mourning the end of his brutal rule — Syria’s future does not look promising.
Polio’s toll
18 Dec, 2024

Polio’s toll

MONDAY’s attacks on polio workers in Karak and Bannu that martyred Constable Irfanullah and wounded two ...
Development expenditure
18 Dec, 2024

Development expenditure

PAKISTAN’S infrastructure development woes are wide and deep. The country must annually spend at least 10pc of its...
Risky slope
Updated 17 Dec, 2024

Risky slope

Inflation likely to see an upward trajectory once high base effect tapers off.
Digital ID bill
Updated 17 Dec, 2024

Digital ID bill

Without privacy safeguards, a centralised digital ID system could be misused for surveillance.
Dangerous revisionism
Updated 17 Dec, 2024

Dangerous revisionism

When hatemongers call for digging up every mosque to see what lies beneath, there is a darker agenda driving matters.