Another Peshawar BRT completion deadline

Published July 9, 2019
The Khyber Pakhtunkhwa government has issued yet another deadline for completion of the much-delayed Bus Rapid Transit project, saying that it will now be operational by the end of current year. — Shahbaz Butt/File
The Khyber Pakhtunkhwa government has issued yet another deadline for completion of the much-delayed Bus Rapid Transit project, saying that it will now be operational by the end of current year. — Shahbaz Butt/File

PESHAWAR: The Khyber Pakhtunkhwa government has issued yet another deadline for completion of the much-delayed Bus Rapid Transit project, saying that it will now be operational by the end of current year.

Details available with Dawn show that currently 85 per cent work on the mega project’s main corridor and 65 per cent on bus depots and staging facility has been complete. The project’s main corridor and feeder routes are to complete by Oct 31, 2019, while Chamkani depot and Dabgari staging facility are expected to be complete by end of September.

However, Hayatabad bus depot is likely to be completed by March 2020.

The payments to contractors have already been made and currently there is no pending claim. The details also show that reservations of the Asian Development Bank, which is funding the project, over some aspects, including bus stations’ finishing, construction of staff toilets in bus stations, Kassel kerb, alignment channels, directional arrows, widening of sharp turns and other issues, have also been addressed.

A recent ADB mission to the project found that about 90 per cent of issues had been resolved, and allowed the Peshawar Development Authority to proceed further in all reaches.

The provincial government and the project’s executing agency, the PDA, had earlier promised opening the project, launched in Oct 2017, within six months on April 20, 2018. However, the deadline was missed. The project managers kept changing the launch dates from May 20 to June 30 to Dec 31 in 2018 to March 23, 2019. The project’s cost has also jumped to Rs68 billion from earlier Rs49 billion.

Published in Dawn, July 9th, 2019

Opinion

Editorial

Kurram atrocity
Updated 22 Nov, 2024

Kurram atrocity

It would be a monumental mistake for the state to continue ignoring the violence in Kurram.
Persistent grip
22 Nov, 2024

Persistent grip

An audit of polio funds at federal and provincial levels is sorely needed, with obstacles hindering eradication efforts targeted.
Green transport
22 Nov, 2024

Green transport

THE government has taken a commendable step by announcing a New Energy Vehicle policy aiming to ensure that by 2030,...
Military option
Updated 21 Nov, 2024

Military option

While restoring peace is essential, addressing Balochistan’s socioeconomic deprivation is equally important.
HIV/AIDS disaster
21 Nov, 2024

HIV/AIDS disaster

A TORTUROUS sense of déjà vu is attached to the latest health fiasco at Multan’s Nishtar Hospital. The largest...
Dubious pardon
21 Nov, 2024

Dubious pardon

IT is disturbing how a crime as grave as custodial death has culminated in an out-of-court ‘settlement’. The...