ECC to decide on LNG plants fuel offtake commitments

Published November 8, 2019
The government has called an urgent meeting of the Economic Coordination Committee (ECC) of the Cabinet on a single-point agenda to remove the condition of 66 per cent compulsory utilisation of Liquefied Natural Gas (LNG) by two mega power projects for facilitate their privatisation as required under the International Monetary Fund programme. — AFP/File
The government has called an urgent meeting of the Economic Coordination Committee (ECC) of the Cabinet on a single-point agenda to remove the condition of 66 per cent compulsory utilisation of Liquefied Natural Gas (LNG) by two mega power projects for facilitate their privatisation as required under the International Monetary Fund programme. — AFP/File

ISLAMABAD: The government has called an urgent meeting of the Economic Coordination Committee (ECC) of the Cabinet on a single-point agenda to remove the condition of 66 per cent compulsory utilisation of Liquefied Natural Gas (LNG) by two mega power projects for facilitate their privatisation as required under the International Monetary Fund programme.

The Ministry of Power has proposed to absolve the power sector of the ‘take-or-pay’ responsibility despite the fact the Pakistan State Oil (PSO), the Sui Northern Gas Pipelines Limited (SNGPL) and the Sui Southern Gas Company Limited (SSGCL) have opposed the proposal on the grounds that they were under international obligations to import LNG for power projects.

These entities have put on record that LNG imports were designed for power sector consumption and their international agreements with Qatar and other private companies involved huge penalties.

In a revised summary to the ECC, the Power Division has reported that the Cabinet Committee on Privatisation (CCoP) had approved 100pc divestment of two LNG power plants through a hybrid option for transaction structure. The CCoP also directed the Power Division to ensure that a certain reasonable percentage of off take be contained in the revised power purchase agreements (PPA) and existing risk matrix should be retained.

It said the LNG imports for Government Power Plants were based on special dispensations that the power complex be operated on must-run basis and in case of non-utilisation of Regassified Liquefied Natural Gas (RLNG), Central Power Purchase Agreement (CPPA) was obligated to pay Net Proceeds Differential and non-supply event be made political force majeure event.

Accordingly, the decision was incorporated in the PPA and the power plants were ensured to operate on must-run basis with a guaranteed off-take of 66pc RLNG in the Gas Supply Agreement (GSA), the Power Division said.

It was also decided by the ECC in 2016 that “in case of privatisation of the Haveli Bahadur Shah and Balloki Projects, the Privatisation Commission before discharging the responsibility under applicable laws and incase of privatisation of Bhihki Project, the ECC, shall review and adjust the risk allocation under the implementation agreement meant exclusively for the said Public Sector Projects at the time.”

Published in Dawn, November 8th, 2019

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Smog hazard
Updated 05 Nov, 2024

Smog hazard

The catastrophe unfolding in Lahore is a product of authorities’ repeated failure to recognise environmental impact of rapid urbanisation.
Monetary policy
05 Nov, 2024

Monetary policy

IN an aggressive move, the State Bank on Monday reduced its key policy rate by a hefty 250bps to 15pc. This is the...
Cultural power
05 Nov, 2024

Cultural power

AS vital modes of communication, art and culture have the power to overcome social and international barriers....
Disregarding CCI
Updated 04 Nov, 2024

Disregarding CCI

The failure to regularly convene CCI meetings means that the process of democratic decision-making is falling apart.
Defeating TB
04 Nov, 2024

Defeating TB

CONSIDERING the fact that Pakistan has the fifth highest burden of tuberculosis in the world as per the World Health...
Ceasefire charade
Updated 04 Nov, 2024

Ceasefire charade

The US talks of peace, while simultaneously arming and funding their Israeli allies, are doomed to fail, and are little more than a charade.