Many NHA projects come to a halt as govt fails to release funds

Published April 5, 2021
NHA contractors did not get payments for the last three months because of non-release of funds. — DawnNewsTV/File
NHA contractors did not get payments for the last three months because of non-release of funds. — DawnNewsTV/File

ISLAMABAD: Billions of rupees’ development projects of the National Highway Authority (NHA) have virtually come to a halt due to a lack of disbursement of funds under the Public Sector Development Programme (PSDP) for the third quarter of the current fiscal year.

The NHA contractors did not get payments for the last three months because of non-release of funds and as a result they adopted a policy of either go-slow or abandoned the infrastructure projects, including those being executed under the China-Pakistan Economic Corridor (CPEC).

However, Minister for Planning and Development Asad Umar said on Sunday that all CPEC-related projects were heading towards completion on a fast pace.

The projects affected are mostly situated in Khyber Pakhtunkhwa, Punjab and Balochistan.

Schemes affected are situated in KP, Punjab and Balochistan

The government allocated Rs119 billion to the NHA in 2020-21, but the ministry concerned released only 30 per cent of the funds, making it difficult for the department to complete the projects in time.

According to an official of the communication ministry, funds for the third quarter were to be released on Jan 1, but they were released in April. The relevant ministries are bound to release PSDP funds to the NHA at the beginning of all four quarters of the fiscal year.

The contractors wait for the release of funds and in case of no-release they purchase construction material on credit and sometimes halt the projects due to non-payment of dues.

The same has happened in the third quarter of the current year when contractors were not paid their dues and they stopped work on the projects.

Major NHA development projects affected due to non-release of funds by the government include Package-6 Rehabilitation of National Highway & Bridges, Fazilpur; D.I. Khan Lot-3 Ramak-D.I. Khan; Construction of Hakla on M-I to Yarik; D.I. Khan Motorway (CPEC) (Rehmani Khel to Kot Balian), Package-2B; Construction of Hakla on M-I to Yarik D.I. Khan Motorway (CPEC), Yarak-Rahmani Khel, Package-I; Dualisation of Old Bannu Road (Gaandi Chowk to Sarai Naurang), Package-3; Dualisation of Old Bannu Road (Khurram to Krapa), Package-2; Dualisation of Old Bannu Road (Domail to Khurram), Package-1; Peshawar Northern Bypass, Packages-2 and 3; Lowari Tunnel, South Access Road, N-45; Lowari Tunnel, North Access Road, N-45; Construction of Khuzdar-Shadadkot Section of Gwadar, Ratodero Road, M-8 Section-IV, Package-III; Construction of black top road Yakmach-Kharan via Dostain Wad Khurmaqai Section-IV; Construction of Hakla on M-I to Yarik D.I. Khan Motorway (CPEC) (Pindi Gheb to Hakla), Packages I, II, III, IV and V; Lahore Eastern Bypass, Package-II; Construction of infrastructure and allied work for Metro Bus Services (Peshawar Morr-Golra Morr), packages-I and II; Dualisation of N-55, Petaro-Sehwan Section, Package-IA; and Dualisation of remaining portion of Sukkur Bypass.

When contacted, a senior official of the NHA, who did not want to be named, told Dawn that the planning division was responsible for the delay in release of funds. He, however, said the finance ministry had released the funds for the third quarter and the NHA would get them on Monday.

Published in Dawn, April 5th, 2021

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Military convictions
Updated 22 Dec, 2024

Military convictions

Pakistan’s democracy, still finding its feet, cannot afford such compromises on core democratic values.
Need for talks
22 Dec, 2024

Need for talks

FOR a long time now, the country has been in the grip of relentless political uncertainty, featuring the...
Vulnerable vaccinators
22 Dec, 2024

Vulnerable vaccinators

THE campaign to eradicate polio from Pakistan cannot succeed unless the safety of vaccinators and security personnel...
Strange claim
Updated 21 Dec, 2024

Strange claim

In all likelihood, Pakistan and US will continue to be ‘frenemies'.
Media strangulation
Updated 21 Dec, 2024

Media strangulation

Administration must decide whether it wishes to be remembered as an enabler or an executioner of press freedom.
Israeli rampage
21 Dec, 2024

Israeli rampage

ALONG with the genocide in Gaza, Israel has embarked on a regional rampage, attacking Arab and Muslim states with...