ISLAMABAD: The Capital Development Authority (CDA) Chairman Amer Ali Ahmed and Director General Frontier Work Organization (FWO) Major General Kamal Azfar, during a visit to Margalla Highway project site, expressed satisfaction over the pace of work.

Both the officers visited entire portion of the said road from Sangjani and D-12.

“The work is continued with full pace and I am hopeful this road from Sanjani to D-12 will be completed months before the deadline,” Chairman CDA told Dawn after his visit.

He said for this portion of the road, the FWO was supposed to complete the work in one year, “but I think, they will complete it by the end of this year,” the chairman said.

During the visit, the CDA chairman was briefed about the ongoing work being executed by FWO on this package of the road.

The CDA chairman said recently after completing contractual formalities, physical work started on the 10-km long Segment-1 from G.T. Road to Sector D-12.

Presently, work has been started simultaneously on road structures and is planned to expand soon to other stretches of the road.

Sources said that the CDA calso directed that there should be no tilt of road near Shah Allah Ditta and a flyover should be constructed to cross a portion of graveyard.

The groundbreaking of the project was performed by Prime Minister Imran Khan in April and CDA after getting special approval from federal cabinet awarded the contract to FWO.

The road will be constructed in two phases - from Sangjani to D-12 and from edge of the Constitution Avenue to Satra Meel, Murree Road, bypassing Bhara Kahu.

CDA is not interested in construction from D-12 to Constitution Avenue as it will use Khayaban-i-Iqbal as a link between both portions of the road.

The CDA chairman said initial survey of the second phase – from edge of Constitution Avenue to Murree Road after bypassing Bhara Kau-- has also been finalized and now the FWO teams are working for detailed design of the said portion.

“I am hopeful the work of this portion will be started after one month and so,” the chairman said and added that the Margalla Road will provide big relief not only to residents of Islamabad but people of other parts of the country and AJK as well.

“After the construction, the chronic issue of traffic congestion at Bhara Kahu area will be resolved,” he said. Currently, the Murree Road at Bhara Kahu area faced constant traffic jam particularly on weekend of summer when people go to Murree.

Published in Dawn, June 19th, 2021

Opinion

Editorial

Smog hazard
Updated 05 Nov, 2024

Smog hazard

The catastrophe unfolding in Lahore is a product of authorities’ repeated failure to recognise environmental impact of rapid urbanisation.
Monetary policy
05 Nov, 2024

Monetary policy

IN an aggressive move, the State Bank on Monday reduced its key policy rate by a hefty 250bps to 15pc. This is the...
Cultural power
05 Nov, 2024

Cultural power

AS vital modes of communication, art and culture have the power to overcome social and international barriers....
Disregarding CCI
Updated 04 Nov, 2024

Disregarding CCI

The failure to regularly convene CCI meetings means that the process of democratic decision-making is falling apart.
Defeating TB
04 Nov, 2024

Defeating TB

CONSIDERING the fact that Pakistan has the fifth highest burden of tuberculosis in the world as per the World Health...
Ceasefire charade
Updated 04 Nov, 2024

Ceasefire charade

The US talks of peace, while simultaneously arming and funding their Israeli allies, are doomed to fail, and are little more than a charade.