KARACHI: The city administration is learnt to have sought directions of the Supreme Court to finalise the demolition of Nasla Tower as one firm sought Rs220 million for razing the high-rise via controlled implosion while the other offered free-of-cost service via mechanical means.

Well-placed sources told Dawn on Sunday that Commissioner Muhammed Iqbal Memon had submitted a report to the apex court informing the pros and cons of both the methods proposed by the two shortlisted companies.

He informed the SC that no company or authority had experience in demolition of a building in urban area through controlled implosion.

He said that a committee of technical experts was constituted for assessing and evaluating the expressions of interest by different companies.

SC asked to decide method for razing the 15-storey building

The SC was informed that the committee recommended a firm, Hi-Tech Electronics and Machinery/DG Demolition, which offered demolition by implosion with all safety measures, seeking 60-day time for demolition and post-demolition work.

The commissioner’s report said the company had given a cost of Rs220m for demolition, including rights on debris and attached valuable material.

It said the building designs had been shared with the firm so that it could prepare a demolition plan.

It was also informed in the report that the committee had also recommended a firm, ANI Enterprises, for demolition of the building through conventional way i.e., with the assistance of machinery and manual labour.

The SC was informed that the firm had given 90 days for the demolition and removal of debris from the site free of charge, claiming the debris inclusive of valuable material. Additionally, the company also offered to pay Rs15m in the government exchequer.

Besides, the SC was informed that the Sindh Building Control Authority had been directed to start pre-demolition work, removal of windows and fulfil other pre-demolition requirement at the earliest and give progress report on a daily basis.

Published in Dawn, November 15th, 2021

Opinion

First line of defence

First line of defence

Pakistan’s foreign service has long needed reform to be able to adapt to global changes and leverage opportunities in a more multipolar world.

Editorial

Eid amidst crises
Updated 31 Mar, 2025

Eid amidst crises

Until the Muslim world takes practical steps to end these atrocities, these besieged populations will see no joy.
Women’s rights
Updated 01 Apr, 2025

Women’s rights

Such judgements, and others directly impacting women’s rights should be given more airtime in media.
Not helping
Updated 02 Apr, 2025

Not helping

If it's committed to peace in Balochistan, the state must draw a line between militancy and legitimate protest.
Hard habits
Updated 30 Mar, 2025

Hard habits

Their job is to ensure that social pressures do not build to the point where problems like militancy and terrorism become a national headache.
Dreams of gold
30 Mar, 2025

Dreams of gold

PROSPECTS of the Reko Diq project taking off soon seem to have brightened lately following the completion of the...
No invitation
30 Mar, 2025

No invitation

FOR all of Pakistan’s hockey struggles, including their failure to qualify for the Olympics and World Cup as well...