NLC to be awarded contract for construction of 10th Avenue in Islamabad

Published November 30, 2021
The file photo captured on May 12, 2020 shows a general view of Islamabad Highway. — AFP/File
The file photo captured on May 12, 2020 shows a general view of Islamabad Highway. — AFP/File

ISLAMABAD: The city managers are all set to award the contract of a mega road project — construction of 10th Avenue — to the National Logistics Cell (NLC).

Four days after the CDA board approved award of the contract to a government-owned company, the authority on Monday conducted a competition between Frontier Works Organisation (FWO) and the NLC and found the latter’s bid of Rs10.2 billion to be the lowest against the Rs10.9 submitted by FWO.

“After completing codal formalities, we will award the contract to NLC,” said an official of the CDA, adding the authority had invited two other government-owned organisations — Railcop and National Construction Company — but they did not participate.

According to CDA officials, 10th Avenue will be constructed in two phases. In the first phase, a five-km road will be constructed from I.J. Principal Road/Katarian Bridge to Srinagar Highway near the edge of G-9 and the starting point of G-10. Once started, work on the project will be completed in 21 months.

The officials said that in future the second phase will be constructed from Srinagar Highway to Margalla Road.

On Wednesday, Executive Committee of the National Economic Council (Ecnec) approved the construction of 10th Avenue from I.J.P Road to Srinagar Highway at a total cost of Rs12.1 billion.

NLC is already executing two major construction projects of CDA: 7th Avenue Interchange and widening and overhauling of I.J.P Road. Work on the two projects is in progress. The FWO is executing the Margalla Road project.

Sources in the CDA said that in a bid to avoid controversies related to the award of contracts, the CDA’s management was focusing on awarding major contracts to government organisations.

“These two companies (FWO and NLC) have full capacity to complete the projects within the deadline. In the past, several projects saw delay due to contractors’ delaying tactics, so now we are hopeful that all the major contracts will be completed well on time,” said an official.

Published in Dawn, November 30th, 2021

Opinion

Editorial

Smog hazard
Updated 05 Nov, 2024

Smog hazard

The catastrophe unfolding in Lahore is a product of authorities’ repeated failure to recognise environmental impact of rapid urbanisation.
Monetary policy
05 Nov, 2024

Monetary policy

IN an aggressive move, the State Bank on Monday reduced its key policy rate by a hefty 250bps to 15pc. This is the...
Cultural power
05 Nov, 2024

Cultural power

AS vital modes of communication, art and culture have the power to overcome social and international barriers....
Disregarding CCI
Updated 04 Nov, 2024

Disregarding CCI

The failure to regularly convene CCI meetings means that the process of democratic decision-making is falling apart.
Defeating TB
04 Nov, 2024

Defeating TB

CONSIDERING the fact that Pakistan has the fifth highest burden of tuberculosis in the world as per the World Health...
Ceasefire charade
Updated 04 Nov, 2024

Ceasefire charade

The US talks of peace, while simultaneously arming and funding their Israeli allies, are doomed to fail, and are little more than a charade.