CHAGAI: Electricity supply to 16 Balochistan cities has been restored after almost eight days, while Quetta is still without power and gas even after two weeks.

Quetta Electric Supply Company (Qesco) spokesman Afzal Baloch told Dawn that the supply was suspended after three pylons carrying 132KV transmission line were damaged due to torrential rains followed by heavy flooding. He said at least 23 grid stations were reconnected to the system after repair work was completed on the Sibi-Quetta double circuit line.

However, the supply of electricity and gas to the provincial capital could not be restored despite the passage of two weeks.

The power supply was suspended when several pylons carrying the Quetta-Sibi transmission line were damaged in Bolan and Sibi areas. Qesco officials said that repair work could not be started as large areas in Sibi and Bolan were still submerged.

However, pipelines at Bibi Nani area in Bolan river could not be repaired due to high flood in the river.

Published in Dawn, September 3rd, 2022

Opinion

Editorial

Military convictions
Updated 22 Dec, 2024

Military convictions

Pakistan’s democracy, still finding its feet, cannot afford such compromises on core democratic values.
Need for talks
22 Dec, 2024

Need for talks

FOR a long time now, the country has been in the grip of relentless political uncertainty, featuring the...
Vulnerable vaccinators
22 Dec, 2024

Vulnerable vaccinators

THE campaign to eradicate polio from Pakistan cannot succeed unless the safety of vaccinators and security personnel...
Strange claim
Updated 21 Dec, 2024

Strange claim

In all likelihood, Pakistan and US will continue to be ‘frenemies'.
Media strangulation
Updated 21 Dec, 2024

Media strangulation

Administration must decide whether it wishes to be remembered as an enabler or an executioner of press freedom.
Israeli rampage
21 Dec, 2024

Israeli rampage

ALONG with the genocide in Gaza, Israel has embarked on a regional rampage, attacking Arab and Muslim states with...