ISLAMABAD: The construction work of 10th Avenue continues at a snail’s pace and it is unlikely that it will be completed in the given deadline of 18 months.

Sources told Dawn that the pace of work shows that this project will take several years to complete as 12 out of 18 months have already passed and so far, the progress on work is less than 15pc.

Work on the project kicked off in March last year and as per the PC-1, the project was slated to be completed in 18 months at a cost of Rs10.2 billion.

This project is funded by the federal government, being executed by Capital Development Authority (CDA).

In the budget for the fiscal year 22-23, the federal government earmarked only Rs350 million for the project; however, only Rs70m have been issued in the first two quarters, considerably slowing the pace of work.

“Without paying required funds to the contractor, National Logistics Cell (NLC), we cannot force the project’s completion within the timeline. The work is in progress at a slow pace and we are hopeful that in April, the federal government will release some funds,” said an officer of CDA, adding that the civic agency has been in contact with the government in this regard.

It is relevant to note here that the NLC, a couple of months ago, had also written a letter to CDA, seeking the required funding for smooth continuation of work.

The official said that there is less than 15pc progress on the work, which includes four bridges.

It is worth mentioning that the project has two phases; in the first phase (currently underway), a 5-kilometre road is being constructed from Katarian Bridge on I.J.P Road to Srinagar Highway near the intersection of G-9 and G-10. In the future, the second phase will be constructed from Srinagar Highway to Margalla Road.

In addition to funding, the CDA could face another issue in this project, as a slum area – Rimsha Colony - near H-9 falls in the alignment of the road and so far, the CDA has not taken any serious step to shift this slum, where there are about 1,400 houses.

“If the project is facing slow pace, this is right time for CDA to resolve the issue of this slum, otherwise, when the contractor will reach here then the civic agency will face another setback, therefore, at least this issue should be resolved for smooth construction of the road,” said a director of CDA.

Published in Dawn, March 17th, 2023

Opinion

Who bears the cost?

Who bears the cost?

This small window of low inflation should compel a rethink of how the authorities and employers understand the average household’s

Editorial

Internet restrictions
Updated 23 Dec, 2024

Internet restrictions

Notion that Pakistan enjoys unprecedented freedom of expression difficult to reconcile with the reality of restrictions.
Bangladesh reset
23 Dec, 2024

Bangladesh reset

THE vibes were positive during Prime Minister Shehbaz Sharif’s recent meeting with Bangladesh interim leader Dr...
Leaving home
23 Dec, 2024

Leaving home

FROM asylum seekers to economic migrants, the continuing exodus from Pakistan shows mass disillusionment with the...
Military convictions
Updated 22 Dec, 2024

Military convictions

Pakistan’s democracy, still finding its feet, cannot afford such compromises on core democratic values.
Need for talks
22 Dec, 2024

Need for talks

FOR a long time now, the country has been in the grip of relentless political uncertainty, featuring the...
Vulnerable vaccinators
22 Dec, 2024

Vulnerable vaccinators

THE campaign to eradicate polio from Pakistan cannot succeed unless the safety of vaccinators and security personnel...