LAHORE: The National Transmission and Despatch Company has completed laying of the 108-km long transmission line of 220kV in south region.

The newly constructed Guddu-Shikarpur transmission line has been energised on June 3. This significant milestone marks a major step towards improving the power supply system in the south areas of Pakistan, specifically Balochistan and Sindh provinces, according a spokesman for the company.

Guddu-Shikarpur Transmission Line project has been completed at a total contract cost of $13.108 million.This transformative project addresses operational problems and system bottlenecks that plagued the previous transmission line. The project will strengthen the connection between Guddu and Shikarpur, resulting in improved stability and reliability of the power transmission network.

The existing 220kV Guddu-Sibbi single circuit transmission line, constructed in 1977, suffered from aging and deterioration of the PCC poles and steel towers. Over the course of its more than 40 years of service, the transmission line experienced a de-rated capacity, causing frequent operational challenges for power transmission from Uch Power plants to respective load centres.

NTDC, the leading national power transmission company, undertook this project as part of its commitment to enhance the country’s power infrastructure. By investing in critical upgrades, NTDC aims to address the increasing demand for electricity and ensure a reliable supply to meet the needs of industries, businesses, and households across Pakistan.

“The Asian Development Bank’s financial support played a crucial role in the realisation of this project. The collaboration between NTDC and ADB exemplifies the commitment of both organisations to sustainable development and the improvement of Pakistan’s power infrastructure,” said the spokesman.

Published in Dawn, June 5th, 2023

Opinion

Editorial

Increased inflows
Updated 12 Jan, 2025

Increased inflows

Govt must devise a strategy to increase industrial and agricultural productivity to boost exports and reduce reliance on uncertain remittances.
Gwadar’s potential
12 Jan, 2025

Gwadar’s potential

THE Gwadar deep-sea port, completed in 2007, was supposed to be a shining success for the other newly built ports in...
Broken metropolis
12 Jan, 2025

Broken metropolis

KARACHI, Pakistan’s economic juggernaut, is the largest contributor to the nation’s tax revenue. The Federal...
Afghan outreach
Updated 11 Jan, 2025

Afghan outreach

Islamabad should stress stronger counterterrorism measures, yet also engage the Taliban high command in Kandahar as well as politicians in Kabul.
Fragile recovery
11 Jan, 2025

Fragile recovery

STATE Bank Governor Jameel Ahmed appears to be quite optimistic over recent economic gains. That is not unusual;...
Destination Europe
11 Jan, 2025

Destination Europe

THE country’s aviation authorities can rest a little easy. After a four-year banishment from European skies,...