Deadly India rail crash caused by faulty signal connections made during repair

Published July 4, 2023
A drone view shows derailed coaches after two passenger trains collided in Balasore district in the eastern state of Odisha, India on June 3. — Reuters
A drone view shows derailed coaches after two passenger trains collided in Balasore district in the eastern state of Odisha, India on June 3. — Reuters

Workers repairing a rail-road barrier in India made faulty connections in the automated signalling system on the network, leading to the country’s worst rail disaster in two decades, an official probe has found.

The June 2 crash at Bahanaga Bazar station, in the eastern Indian state of Odisha, killed 288 people and injured more than 1,000.

The disaster struck when a passenger train hit a stationary freight train, jumped off the tracks and hit another passenger train coming from the opposite direction.

In the probe report, seen by Reuters, the Commission of Railway Safety (CRS) investigators said the first collision occurred due to modifications done to the signalling circuit to fix frequent problems at a nearby rail-road barrier.

Local railway staff did not have a standard circuit diagram which led to a faulty connection in the signalling system when they tried to take the boom-barrier circuit offline for repair, it said. The malfunctioning system directed the passenger train onto the path of the freight train, it said.

Reuters last month reported for the first time that investigators were focusing on the repair work on the railroad barrier and its possible connection to a manual bypass of the signalling system.

Indian Railways, the fourth largest train network in the world, is a state monopoly run by the Railway Board. The board reports to the Railways Ministry.

The rail network is undergoing a $30 billion transformation with gleaming new trains and modern stations under Prime Minister Narendra Modi’s push to boost infrastructure and connectivity but the crash raised questions about whether safety was getting enough attention.

The CRS probe report said there were lapses at multiple levels in the signal and telecom department and standard operating procedures were not followed during the repair work.

Opinion

Editorial

Bilateral progress
Updated 18 Oct, 2024

Bilateral progress

Dialogue with India should be uninterruptible and should cover all sticking points standing in the way of better ties.
Bracing for impact
18 Oct, 2024

Bracing for impact

CLIMATE change is here to stay. As Pakistan confronts serious structural imbalances, recurring natural calamities ...
Unfair burden
18 Oct, 2024

Unfair burden

THINGS are improving, or so we have been told. Where this statement applies to macroeconomic indicators, it can be...
Successful summit
Updated 17 Oct, 2024

Successful summit

Platforms like SCO present an opportunity for states to set aside narrow differences.
Failed tax target
17 Oct, 2024

Failed tax target

THE government’s plan to document retailers for tax purposes through its ‘voluntary’ Tajir Dost Scheme appears...
More questions
17 Oct, 2024

More questions

THE alleged rape of a student at a private college in Lahore has sparked confusion, social media campaigns, ...