No further extension in Sukkur Barrage rehabilitation project: WB official

Published November 3, 2023
WORLD Bank officials, in the front row, listen to chief engineer of Sukkur Barrage.—Photo by the writer
WORLD Bank officials, in the front row, listen to chief engineer of Sukkur Barrage.—Photo by the writer

SUKKUR: World Bank’s water resources management specialist Theruni Liyanage has urged the need to complete rehabilitation and modernisation of Sukkur Barrage in its stipulated period of four years, clearly stating that no further extension will be granted.

She was part of the World Bank Implemention Support Mission which reviewed the work progress of the barrage on Thursday, led by WB practice manager Mr Josses Mugabi.

Briefing the mission on the occasion, Sukkur Barrage Chief Engineer Syed Sardar Ali Shah suggested that a trail gate without counter weight should be installed at the weir instead of the pocket before the flood season as “we can observe the operation of the trail gate without counter weight of 80 tonne to reduce the extra load on the barrage”.

Sindh Barrages Improvement Project (SBIP) Deputy Director Abdul Razak Memon said the provision of the trail gate for physical demonstration had already been kept in the scope of the rehabilitation and modernisation of the Sukkur Barrage contract.

Ms Liyanage, who is also co-task team leader of the WB, said that it had been observed that the progress of the work of Sukkur barrage was continued according to the proper schedule.

She advised that there was also need to improve the health, safety environment.

Mr Mugabi said the methodology of the rehabilitation of Sukkur Barrage was organised, but it needed strengthening of the weaknesses.

He said that according to the suggestion and guidelines of a panel of experts and departments’ technical personnel and international consultants, the design work of the barrage was in progress.

The World Bank mission also visited the Indus Blind Dolphins Center, and ongoing construction works related to the SBIP, including the mechanical workshop and engineering works.

Those who accompanied the team included Coordination and Monitoring Unit of Planing and Development’s Project Coordi-nator Nazir Essani, Sociologist Ghulam Hyder Qureshi, Director Ghulam Murtaza Abro and others.

Published in Dawn, November 3rd, 2023

Opinion

Editorial

Rushed legislation
Updated 06 Nov, 2024

Rushed legislation

For all its stress on "supremacy of parliament", the ruling coalition has wasted no opportunity to reiterate where its allegiances truly lie.
Jail reform policy
06 Nov, 2024

Jail reform policy

THE state is making a fresh attempt to improve conditions in Pakistan’s penitentiaries by developing a national...
BISP overhaul
06 Nov, 2024

BISP overhaul

IT has emerged that the spouses of over 28,500 Sindh government employees have been illicitly benefiting from BISP....
Smog hazard
Updated 05 Nov, 2024

Smog hazard

The catastrophe unfolding in Lahore is a product of authorities’ repeated failure to recognise environmental impact of rapid urbanisation.
Monetary policy
05 Nov, 2024

Monetary policy

IN an aggressive move, the State Bank on Monday reduced its key policy rate by a hefty 250bps to 15pc. This is the...
Cultural power
05 Nov, 2024

Cultural power

AS vital modes of communication, art and culture have the power to overcome social and international barriers....