QUETTA: A special audit report has revealed irregularities of Rs2.4 billion and delays in the construction of 100 dams in Balochistan.

It added that work on 26 out of 100 dams was completed in 2021 instead of 2018. The delay ballooned construction costs by Rs261 million.

Expenses of the project implementation unit and supervision also went up by Rs133.6m, the report added.

An additional payment of Rs112.6m was made to non-shareholders while contractors were charged Rs9.9m less than what they owed under income tax.

An unregulated expenditure of over Rs950m was made for completion and another Rs150m for laboratory tests, which weren’t conducted. Rs131.8m were also spent on soil extraction and blasting of rocks, the report added.

The report has recommended action against those responsible for the misappropriation of funds.

Published in Dawn, May 19th, 2024

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

‘Cruel jest’
Updated 02 Jul, 2024

‘Cruel jest’

Actual economic course correction has once again been put off for another time.
Limited choices
02 Jul, 2024

Limited choices

NONE of the limited choices before the international community where dealing with the Afghan Taliban regime are very...
India’s victory
02 Jul, 2024

India’s victory

IN the end, the best team won — the team that held its nerve best when the stakes were the highest. Batting...
Resolution 901
Updated 01 Jul, 2024

Resolution 901

Our lawmakers’ failure to stand united in the face of foreign criticism may not have been unexpected but it was still disturbing to witness.
Nebulous definition
01 Jul, 2024

Nebulous definition

IS it a ‘vision’, a loose programme, or an actual kinetic ‘operation’? A week on, we don’t precisely know....
Stealing heritage
01 Jul, 2024

Stealing heritage

CONTRADICTIONS define Pakistan. While the country’s repository of antiquities can change its fortunes, recurrent...