QUETTA: A special audit report has revealed irregularities of Rs2.4 billion and delays in the construction of 100 dams in Balochistan.

It added that work on 26 out of 100 dams was completed in 2021 instead of 2018. The delay ballooned construction costs by Rs261 million.

Expenses of the project implementation unit and supervision also went up by Rs133.6m, the report added.

An additional payment of Rs112.6m was made to non-shareholders while contractors were charged Rs9.9m less than what they owed under income tax.

An unregulated expenditure of over Rs950m was made for completion and another Rs150m for laboratory tests, which weren’t conducted. Rs131.8m were also spent on soil extraction and blasting of rocks, the report added.

The report has recommended action against those responsible for the misappropriation of funds.

Published in Dawn, May 19th, 2024

Follow Dawn Business on Twitter, LinkedIn, Instagram and Facebook for insights on business, finance and tech from Pakistan and across the world.

Opinion

Editorial

Bilateral progress
Updated 18 Oct, 2024

Bilateral progress

Dialogue with India should be uninterruptible and should cover all sticking points standing in the way of better ties.
Bracing for impact
18 Oct, 2024

Bracing for impact

CLIMATE change is here to stay. As Pakistan confronts serious structural imbalances, recurring natural calamities ...
Unfair burden
18 Oct, 2024

Unfair burden

THINGS are improving, or so we have been told. Where this statement applies to macroeconomic indicators, it can be...
Successful summit
Updated 17 Oct, 2024

Successful summit

Platforms like SCO present an opportunity for states to set aside narrow differences.
Failed tax target
17 Oct, 2024

Failed tax target

THE government’s plan to document retailers for tax purposes through its ‘voluntary’ Tajir Dost Scheme appears...
More questions
17 Oct, 2024

More questions

THE alleged rape of a student at a private college in Lahore has sparked confusion, social media campaigns, ...