ISLAMABAD: The Capital Development Authority (CDA) on Wednesday contended before the Islamabad High Court (IHC) that it was “unjustly penalised” in the Parliament Lodges extension project case.

During the hearing of a case related to an arbitration award that bound CDA to pay Rs640 million to private contractor Habib Rafiq (Private) Limited, CDA’s counsel Kashif Ali Malik questioned the legality of the arbitrator’s decision.

IHC Chief Justice Aamer Farooq heard the case.

The civic agency’s counsel contested that the award was unjust and placed an undue financial burden on the public exchequer.

Civic body’s council argues Rs640 million penalty unjustified; urges court to reverse ruling

The Parliament Lodges extension project originally launched to provide housing for lawmakers, has been plagued by multiple delays, cost escalations and contractual disputes.

Initially, the contractor was assigned to construct 104 family suites and 500 servant quarters by November 2013.

However, the civic agency extended the deadline to 2014.

In 2015, the CDA imposed a fine on the contractor for failing to meet the deadline. Instead of paying the fine, the contractor invoked the jurisdiction of an arbitration tribunal to settle the case. After hearing the dispute, arbitrator retired Justice Nasir Aslam Zahid imposed a penalty of Rs640 million on CDA.

When CDA delayed the payment, the contractor approached a civil court through its lawyer and pressed the development authority to pay the penalty. The civic body, however, objected to the proceedings, saying that under the law, the arbitrator was only empowered to submit the report.

The civil court ruled in favour of the CDA and the contractor went on to move the IHC where a single-member bench initially dismissed the plea but later ruled in favour of the contractor.

The contractor then filed a petition seeking execution of the award.

During Wednesday’s hearing, Justice Farooq sarcastically remarked that IHC’s building was also a classic example of the construction skills of the same builder.

Interestingly, the loopholes in the IHC building were revealed following the malfunctioning of an elevator that was carrying Sardar Latif Khan Khosa, the counsel for former prime minister Imran Khan. During the episode, the former premier’s lawyer was stranded along with 18 others for over 40 minutes inside the faulty elevator.

Following the incident, the court ordered an inquiry into the malfunctioning and sought a report.

The construction of the IHC building started in November 2013 and it took about a decade to complete the project.

The building became operational in June 2023. However, when the high court was moved to the new building on Constitution Avenue, several loopholes emerged in the construction, it was reported.

The heating, ventilation and air conditioning system which had cost Rs550 million went out of order right from the beginning.

Other issues coupled with the elevator gaffe hinted that the building posed serious threats to the lives of litigants, lawyers, court staffers and even judges of the high court.

Moreover, the boundary wall of the IHC collapsed, prompting the Pakistan Public Works Department to write a letter to the housing ministry. In the letter, the department stated that the filtration plant of the newly constructed IHC building was also not functioning properly, reflecting subpar construction by the contractor.

Published in Dawn, January 30th, 2025

Opinion

The price of chocolate

The price of chocolate

Little attention is paid to any long-term strategy which might prevent vulnerable children from working in homes where they are in danger.

Editorial

Cholistan project
Updated 18 Feb, 2025

Cholistan project

GPI goals align with Pakistan's broader economic aims but the manner in which the initiative was launched raises questions.
Right to know
18 Feb, 2025

Right to know

IT is an unfortunate paradox that while on paper Pakistan has some of the most impressive right to information laws,...
Dam dispute
18 Feb, 2025

Dam dispute

THE situation in Chilas needs attention and a fair-minded approach so that it can be resolved amicably. Diamer ...
Climate funding gap
Updated 17 Feb, 2025

Climate funding gap

Pakistan must boost its institutional capacity to develop bankable climate projects.
UN monitoring report
Updated 17 Feb, 2025

UN monitoring report

Pakistan must press Kabul diplomatically over its tolerance of TTP terrorism.
Tax policy reform
17 Feb, 2025

Tax policy reform

THE cabinet’s decision to create a Tax Policy Office at the finance ministry has raised hopes that tax policy is...