Two gas pipelines blown up

Published February 10, 2008

QUETTA, Feb 9: Suspected militants blew up two main gas pipelines in the Tali Matt and Tangwani areas of Dera Bugti district on Saturday, disrupting supply to a Sui purification plant besides parts of Quetta.

The Sui Southern Gas Company (SSGC) had to stop supply to the industrial units, CNG stations and a private power plant in order to continue supplying gas to the provincial capital and other areas including four districts.

According to official sources, militants planted an explosive device under a 21-inch diameter pipeline in Tali Mat area, located between Sui and Dera Bugti. The pipeline supplies gas from Pir Koh gas field to the purification plant.

Soon after the blast, engineers and other staff of the company reached the place and started the repairing work.

In another incident, an 18-inch diameter main pipeline supplying gas to Quetta and other areas of the province from Sui was also blown up by militants in the Tangwani area of Dera Bugti district.

“Around five feet long piece of the pipeline was blown up in the blast that was carrying 110 MMCFD gas from Sui to Quetta,” SSGC officials confirmed.

Meanwhile, a spokesman for the Baloch Republican Army, identifying himself as Sherbaz Baloch, claimed the responsibility for both the bombings.

Opinion

Editorial

Taking cover
Updated 09 Jan, 2025

Taking cover

IT is unfortunate that, instead of taking ownership of important decisions, our officials usually seem keener to ...
A living hell
09 Jan, 2025

A living hell

WHAT Donald Trump does domestically when he enters the White House in just under two weeks is frankly the American...
A right denied
09 Jan, 2025

A right denied

DESPITE citizens possessing the constitutional and legal right to access it, federal ministries are failing to...
Closed doors
Updated 08 Jan, 2025

Closed doors

The nation’s fate has been decided through secret deals for too long, with the result that the citizenry has become increasingly alienated from the state.
Debt burden
08 Jan, 2025

Debt burden

THE federal government’s total debt stock soared by above 11pc year-over-year to Rs70.4tr at the end of November,...
GB power crisis
08 Jan, 2025

GB power crisis

MASS protests are not a novelty in Pakistan, and when the state refuses to listen through the available channels —...