ISLAMABAD, Aug 30 As Chitral is facing worst ever electricity crisis, a tug of war among the politicians coupled with rampant mismanagement and inefficiency of the local power utility officials have further compounded the miseries of the consumers leaving no room for resolution of the problem.

Though small hydropower units have been set up and are working efficiently even in remote villages of the valley through monetary and technical know-how provided by the private sector, power crisis in the main town having a population of about 40,000 has deteriorated during the last a couple of years.

The local power house generates about one megawatt; 1.2 megawatts are supplied from the Reshun hydropower station in the Mastuj tehsil while about 1.5 megawatts come from the national grid against the total demand of about three megawatts.

However, the consumers allege that the Pesco officials show the production of Chitral town powerhouse at 600 kw and do not give account for the electricity coming from Reshun and the national grid.

The consumers say sufficient electricity is available in the town and more can be generated with ease, but local political leaders have messed up with the issue for their own vested interests.

All the political leaders including the district nazim of Jamaat-i-Islami, a provincial minister belonging to the PPP and the PML-Q MNA have played games for their own vested interests.

When one leader tries to resolve the issue, others waste no time to sabotage his efforts lest he gets credit for it.

Fed up with the power breakdowns some time stretching up to over 20 hours daily, thousands of consumers led by convener Movement for Restoration of Electricity Wg Cdr (retired) Fardad Ali shah took to the streets recently demanding transparency in utilisation of the available electricity and investigation into alleged mismanagement, corruption and misuse of authority by the Pesco officials.

Members of the movement claimed that the local power station was producing over one megawatt, its maximum rated output with two turbines, but there was no record where the remaining 400 kw was being utilised.

The powerhouse has 55 employees most of whom remain absent from duty.

Strangely, each employee is enjoying 600 units free electricity which they scrounge up to 4,000 units by subletting free electricity to others.

The local powerhouse has five generators which are never operated even though fuel was provided for them by the local administration.

The consumers said the resident engineer of the power house had refused to operate the generators. The consumers alleged that essential parts of the generators had already been sold out by the officials.

Opinion

Editorial

PTI in disarray
Updated 30 Nov, 2024

PTI in disarray

PTI’s protest plans came abruptly undone because key decisions were swayed by personal ambitions rather than political wisdom and restraint.
Tired tactics
30 Nov, 2024

Tired tactics

Matiullah's arrest appears to be a case of the state’s overzealous and misplaced application of the law.
Smog struggle
30 Nov, 2024

Smog struggle

AS smog continues to shroud parts of Pakistan, an Ipsos survey highlights the scope of this environmental hazard....
Solidarity with Palestine
Updated 29 Nov, 2024

Solidarity with Palestine

The wretched of the earth see in the Palestinian struggle against Israel a mirror of themselves.
Little relief for public
29 Nov, 2024

Little relief for public

INFLATION, the rate of increase in the prices of goods and services over a given period of time, has receded...
Right to education
29 Nov, 2024

Right to education

IT is troubling to learn that over 16,500 students of the University of Karachi (KU) have defaulted on fee payments...