DAWN.COM

Today's Paper | November 22, 2024

Published 14 Jul, 2012 02:48am

Hydropower project opening today

LAHORE, July 13: The 72 megawatt Khan Khwar High-head Hydropower Project will formally be inaugurated on Saturday (today).

The project will provide 306 million units of low-cost electricity per annum to the National Grid. Annual benefits of the project have been estimated at more than Rs2.75 billion.

The project has been constructed on Khan Khwar (Nullah), a right bank tributary of the River Indus near Besham Town in Shangla District of Khyber Pakhtunkhwa – some 265 kilometres from Islamabad and 350 kilometres from Peshawar on Karakuram Highway.

Main component of the project includes a 46-metre high and 112-metre long dam, about five-kilometre long tunnel, a power house and a switchyard.

The project is connected with the National Grid through a 132/220 Kilo Volt (KV) transmission line constructed for three high-head hydropower projects.

The project has been completed with a cost of Rs10.73 billion that includes Rs5.049 billion as foreign exchange component. Islamic Development Bank provided a loan amounting to $30.8 million for the project.

Khan Khwar Hydropower Project is a part of least-cost energy generation plan of Wapda being executed on priority in view of the increasing demand of electricity in the country.

Under the plan, 17 large projects are under construction/at detailed engineering stage, which will generate more than 20,000MW. Of them, six hydropower projects with a cumulative generation capacity of about 400MW will be completed during the current year.

Prominent amongst the rest of the 11 projects are 969MW Neelum-Jhelum, 106MW Golen Gol, 4500MW Diamer Basha Dam, 1,410MW Tarbela’s 4th Extension, 84MW Kurrum Tangi, 4,320MW Dasu, 740MW Munda and 7,100MW Bunji etc.

Read Comments

IHC grants Imran bail in new Toshakhana case as govt rules out release Next Story