BAHAWALPUR: After missing the deadline for completion twice, construction of the Bahawalpur railway station has picked up pace, which is visible at the site.

The three-storey building, including 6,080 square feet basement and 3,186 sq ft ground floor, costing over Rs278 million is slated to be a state-of-the-art building covering an area of 43,500 sq ft.

Construction work of the project had been started on June 8, 2016 and was scheduled to be completed by Dec 31, 2017, but due to unforeseen circumstances it was delayed.

During a visit to the site, contractor National Logistics Cell’s retired Maj Arshad Ghumman and consultant National Engineering Services Pakistan’s Muhammad Irfan Bhatti told Dawn that 75 per cent of construction work of the basement, and ground, first and second floors had been completed and finishing work was under way. This was expected to be completed within three months after which the building could be handed over to Pakistan Railways for opening and operations. They said the ground floor could even be operational in June.

The key features of the new railway station would be found on the ground floor, including reservation office, IT room, information and advance ticketing office, a large covered sitting area and shops to generate revenue for the railways department.

The VIP waiting room, waiting halls, outward/inward parcel rooms, prayer and ablution area and station master’s office would be situated on the first floor while the second floor will house the assistant station master’s office, power room and equipment room. There will be a capacity of parking 89 cars and over 400 motorcycles outside the building.

Published in Dawn, May 14th, 2018

Opinion

Editorial

Genocide resumes
Updated 19 Mar, 2025

Genocide resumes

It appears that Palestinian people will again be left defenceless in the face of merciless brutality.
Strength in unity
19 Mar, 2025

Strength in unity

WILL it count as an opportunity lost? Given the sharp escalation in militant violence in recent weeks, some had ...
NFC weightage
19 Mar, 2025

NFC weightage

THE NFC Award has long been in need of an overhaul. The government’s proposal to bring down the weightage of...
A new direction
Updated 18 Mar, 2025

A new direction

While kinetic response may temporarily disable violent actors, it will not address underlying factors providing ideological fuel to insurgencies.
BTK settlement
18 Mar, 2025

BTK settlement

WHEREVER the money goes, controversy follows. The PMLN-led federal government, which recently announced that it will...
Sugar crisis
18 Mar, 2025

Sugar crisis

GREED knows no bounds. But the avarice of those involved in the sugar business — from manufacturers to retailers...