ISLAMABAD: Margalla Avenue, which was supposed to be completed in June 2013, remains unfinished seemingly due to disinterest on the part of the Capital Development Authority (CDA).

Construction on the project began in 2012, but it was stopped a few years ago when the CDA was unable to build a portion of the road near Shah Allah Ditta due to a centuries old graveyard, a shrine and the alignment of the road.

CDA engineers said that the alignment of the road should have been cleared before the project began, but the authority initiated it in haste. The nine kilometre road between the G.T. Road and D-12 has therefore remained incomplete, with 51pc of the work finished.

A CDA official said that if completed the project could relieve traffic congestion on Kashmir Highway and facilitate traffic from the G.T. Road heading towards Murree and Kashmir.

They said that if the road was even completed up to D-12 it could be connected to Khayaban-i-Iqbal, commonly known as Margalla Road, to get to Parliament House from where it would be connected to Murree Road via Bari Imam.

The official said a 2km portion of Margalla Road north of Constitution Avenue towards Bari Imam has already been built but has been abandoned for years because some of the work remains unfinished.

CDA officials said one of the main reasons for the delay in the completion of Margalla Avenue between the G.T. Road and D-12 is a dispute between the contractor and the CDA.

When work was stopped a few years ago, the contractor had filed a case against the CDA arguing that the CDA was responsible for clearing the land for the construction of the road and should therefore pay the contractor. The CDA has claimed the contract was cancelled for other technical reasons.

A court arbitrator fined the CDA Rs170 million, which the authority challenged in the Islamabad High Court.

CDA spokesperson Syed Safdar Ali said the case in the high court and “we are pursuing the case vigorously.”

He said the CDA is also working on proposals to remove the bottleneck in this project.

The CDA awarded a Rs588m contract for the project – 21pc below its estimated cost – but CDA officials said it was started in haste due to political pressure before necessary steps, such as land acquisition in some pockets of alignments, were completed.

The CDA had proposed changing the alignment of the road in an area where there was a bottleneck a few years ago, but sources said no serious efforts were made to remove the hindrance.

Published in Dawn, September 12th, 2019

Editorial

Shocking ambush
Updated 13 Mar, 2025

Shocking ambush

The sophistication of attack indicates that separatists likely had support from experienced external players.
Suffocating crisis
13 Mar, 2025

Suffocating crisis

THREE of the five countries with the most polluted air on Earth are in South Asia. They include Pakistan, which has...
Captive grid
13 Mar, 2025

Captive grid

IT is a common practice: the government makes commitments with global lenders for their money and then tries to...
State Bank’s caution
Updated 12 Mar, 2025

State Bank’s caution

Easing monetary policy will be difficult for SBP without large, sustainable foreign capital inflows and structural tax reforms.
Syria massacre
12 Mar, 2025

Syria massacre

THERE were valid fears of sectarian and religious bloodshed when anti-Assad militants triumphantly marched into...
Too little, too late
12 Mar, 2025

Too little, too late

WHEN desperation reaches a point that a father has to end his life to save his daughter’s, the state has failed ...