DADU: The danger of Manchhar Lake overtopping its banks during floods has been reduced by 70 per cent after increase in number of discharge gates from five to 12 at Aral Wah head regulator, which will help enhance the discharge from 12,000 cusecs to 52,000 cusecs and bring the lake’s level down from two inches to one foot within 24 hours, according to irrigation officials.

A World Bank mission comprising Ahsen Tehsin, Rehan Hyder, Ms Nihan Rafique, project director Javed Memon and Zahid Sheikh, which is currently on a three-day visit to review progress on the WB-funded Sindh Resilience Project (SRP) and Sindh Flood Emergency Rehabilitation Project (SFERP) was informed at its first review meeting with irrigation officials in Karachi on Wednesday that the lake’s embankment had also been raised by another two feet throughout its stretch of 30 kilometres and widened from 20 feet to 30 feet.

The SFERP is concerned with repairing the damage caused by floods in 2022 and has undertaken rehabilitation activities to normalise daily life in flood-hit areas.

The meeting was informed that 11 small dams had been built in areas surrounding Karachi to control urban flooding under this project, three pumping stations had been rehabilitated in Khairpur district for the disposal of stagnant rainwater and a storm water drain was constructed in Shaheed Benazirabad town to avert flooding of area due to rains.

The meeting was told that SRP had so far been able to build 70 small dams in the drought-hit areas of the province for the provision of drinking water as well as for irrigation purposes, which led to harvest of bumper agricultural produce in the areas like Thar where it had helped local population to have two crops in a year bringing an overall change in the socio- economic conditions by raising their living standards.

The meeting said the impact assessment study of building the small dams was being carried out by Mehran University of Engineering and Technology which would be completed by Aug 31, 2024, and the SRP was scheduled to close on June 30.

The meeting also reviewed utilisation of funds under both the projects and found out that the funds allocated for the activities had been fully utilised in a transparent manner.

Published in Dawn, May 30th, 2024

Opinion

First line of defence

First line of defence

Pakistan’s foreign service has long needed reform to be able to adapt to global changes and leverage opportunities in a more multipolar world.

Editorial

Eid amidst crises
Updated 31 Mar, 2025

Eid amidst crises

Until the Muslim world takes practical steps to end these atrocities, these besieged populations will see no joy.
Women’s rights
Updated 01 Apr, 2025

Women’s rights

Such judgements, and others directly impacting women’s rights should be given more airtime in media.
Not helping
Updated 02 Apr, 2025

Not helping

If it's committed to peace in Balochistan, the state must draw a line between militancy and legitimate protest.
Hard habits
Updated 30 Mar, 2025

Hard habits

Their job is to ensure that social pressures do not build to the point where problems like militancy and terrorism become a national headache.
Dreams of gold
30 Mar, 2025

Dreams of gold

PROSPECTS of the Reko Diq project taking off soon seem to have brightened lately following the completion of the...
No invitation
30 Mar, 2025

No invitation

FOR all of Pakistan’s hockey struggles, including their failure to qualify for the Olympics and World Cup as well...